Page 39 - A-client-guide-to-working-with-a-SAIA-architect
P. 39

The work
    stages of an

    architect’s
    service          Stage 5 – Construction


                     Work stage five commences when the architect as principal agent hands over the site to the contractor
          6  1 2
                     and issues the contract documentation, drawings and schedules required. The site boundaries and
                     servitudes are pointed out by the appointed land surveyor. The contractor then sets up the site camp,
                3
                     sets out the work and construction commences.
      5
              4      The architect arranges, chairs and records regular site meetings with the contractor and the other
                     consultants and agents as required. The process is to inspect and monitor the works to ensure the
                     contract is adhered to and the obligations will be achieved.
                     This will include reviewing samples of materials and work and mock-ups provided by the contractor
                     both on and off site, updating and issuing a register of drawings and documents issued, as well as